Changes between Version 2 and Version 3 of Research/DesignStudy/Meetings/2019-06-25-LhARA


Ignore:
Timestamp:
Jun 30, 2019 9:22:48 PM (5 years ago)
Author:
longkr
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/DesignStudy/Meetings/2019-06-25-LhARA

    v2 v3  
    2727  * Argue that can do in-vitro concept now to October.  Then, with support, do FFA and in-vivo set-up, and deliver outline CDR.
    2828  * **JPa** agreed to draft this answer.
    29 
    3029 2. "Please also clarify the work required to upgrade the CCC beamline to facilitate FLASH." \\
    3130 Points noted:
     
    3433 * JPo noted the importance of defining what we mean by FLASH.
    3534 * **JPrsns** agreed to draft this answer.
    36 
    3735 3. "The project covers 24 months, while funding is requested for two PDRAs for 6 months each.  Please clarify the project plan ; what work the PDRAs will do, and when, and what work is required by other researchers." \\
    3836 Points we discussed:
     
    4240 * We noted that we would explain that for the CCC b/line work, the dosimetry activity would be rapid, then move on to experiment work funded through other routes.
    4341 * **KL** agreed to draft this answer.
    44 
    4542 4. "Clarify the value added by this proposal to the overall LhARA project." \\
    4643 We noted: