Preparation of pre-CDR for LhARA

Last updated: 11Nov19 [KL]

An effort to develop a 'pre-CDR' has been initiated supported by the award of an STFC Opportunities 2019 award. This page is being used to collect and share information in the preparation of the pre-CDR.

Key dates

  • 29 Nov 2019: First issue of the baseline. This will include lists from the various systems of what needs to be updated on the existing floor layout, WBS, interfaces document and the parameter table.
  • 31 Dec 2019: First end-to-end tracking simulation.
  • 31 Jan 2020:
    • Design of the facility will be frozen.
    • First view of the costs.
    • R&D programme needed to realise LhARA and be able to write a technical design report will be defined.
  • 28 Feb 2020: Complete the write-up of the pre-CDR.
  • Mar 2020: External review of pre-CDR in advance of publication.

Steering Group

  • Meetings
    • 28 Nov 2019 10:00 GMT
    • 17 Dec 2019 10:00 GMT
    • 31 Jan 2020 10:00 GMT
    • 28 Feb 2020 10:00 GMT

Project management information

Work package managers

The following table lists the work packages, managers and contact details. NB: you need to be logged in to see the full email link.

Work package Manager(s) Email
Laser driven proton and ion source Zulfikhar Najmudin
Oliver Ettlinger
z.najmudin@…
o.ettlinger13@…
Proton and ion capture Juergen Pozimski
Colin Whyte
j.pozimski@…
colin.whyte@…
Stage 1 beam transport: Beam transport and delivery to the in vitro end station Jaroslaw Pasternak
William Shields
j.pasternak@…
William.Shields.2010@…
Stage 2 beam transport: Post-acceleration and beam delivery to the in vivo end station Jaroslaw Pasternak
William Shields
j.pasternak@…
William.Shields.2010@…
Biological end stations Jason Parsons
Jonathan Hughes
J.Parsons@…
Jonathan.Hughes@…
Infrastructure and Integration John Thomason
Galen Aymar
john.thomason@…
galen.aymar@…
Project plan for the delivery of LhARA Ajit Kurup a.kurup@…
Safety John Thomason
Galen Aymar
john.thomason@…
galen.aymar@…
End-to-end simulation Ajit Kurup a.kurup@…
Instrumentation TBD

Floor plan