Preparation of pre-CDR for LhARA

Last updated: 11Nov19 [KL]

An effort to develop a 'pre-CDR' has been initiated supported by the award of an STFC Opportunities 2019 award. This page is being used to collect and share information in the preparation of the pre-CDR.


Key dates

  • 29Nov19: First issue of the baseline. This will include the floor layout, WBS, Interfaces document and the parameter table.
  • 31Dec19: First end-to-end tracking simulation.
  • 31/1/20:
    • Design of the facility will be frozen.
    • First view of the costs.
    • R&D programme needed to realise LhARA and be able to write a technical design report will be defined.
  • 28Feb20: Complete the write-up of the pre-CDR.
  • Mar20: External review of pre-CDR in advance of publication.

Project Management information