1 | | = Temp = |
| 1 | = SmartPhantom meetings: Wednesday 4^th^ December 2019; 11:00 GMT = |
| 2 | |
| 3 | == Summary of actions: == |
| 4 | * **KL**: Liaise to develop concept for polishing. |
| 5 | * **KL/LC**: Visit C.Lockett and to confirm potting arrangements. |
| 6 | * **KL/LC**: Check that drawing pack on the WWW is up to date. |
| 7 | |
| 8 | == Notes: == |
| 9 | |
| 10 | 1. Notes and actions from [wiki:Research/Instrumentation/Meetings/2019/11-20 last meeting]: |
| 11 | * **KL**: Liaise to develop concept for polishing. |
| 12 | * **Stands.** |
| 13 | |
| 14 | 2. Mechanical design/manufacture update: LC |
| 15 | No update this week. \\ |
| 16 | LC will arrange for KL to visit C.Lockett tomorrow. KL and LC will check that the drawing pack on the wiki is uptodate. |
| 17 | |
| 18 | 3. Single-fibre/fibre-bundle test setup: HTL |
| 19 | HTL has carried out an extended search for scintillation light excited by the ^90^Sr source from single fibre. He has not found a signal above background in a scan over the source. Consistent explaination is that light excited by the source is insufficient. |
| 20 | * AK: suggests to histogram responses from a particular pixel. HTL will pursue using the data that has been recorded. |
| 21 | |
| 22 | HTL now prepring a 'pig-tail' of scintillating fibre that can be illuminated by the UV LED, the source and a proton beam at Clatterbridge. |
| 23 | |
| 24 | 4. Schedule revision discussion: All \\ |
| 25 | **Agreed** to move on to production of pig-tail and winding of clear-fibre light guides. |
| 26 | |
| 27 | 5. Spend: outstanding requirement: All \\ |
| 28 | Outstanding items: |
| 29 | * Cameras; |
| 30 | * Cf for the full SmartPhantom. We have enough for the prototype. |
| 31 | * May also need extra fibre since we've decided to build the pig-tail. |
| 32 | |
| 33 | 6. Next steps: All \\ |
| 34 | As above. |
| 35 | |
| 36 | 7. DONM \\ |
| 37 | Wed. 11Dec19. |
| 38 | |
| 39 | 8. AoB \\ |
| 40 | * We discussed the need to contact MedAustron/MedUniWien re delays. KL will consider and take forward. |
| 41 | |
| 42 | ---- |
| 43 | |
| 44 | == Meeting details == |
| 45 | |
| 46 | Venue: 1105 Blackett Laboratory. |
| 47 | |
| 48 | Videoconference using the Vidyo system. |
| 49 | |
| 50 | Connection details: \\ |
| 51 | Please join the VIDYO meeting by clicking this link: https://vidyoportal.cern.ch/join/SPJlsfAOEV |
| 52 | |
| 53 | ---- |
| 54 | |
| 55 | == Agenda: == |
| 56 | |
| 57 | 1. Notes and actions from [wiki:Research/Instrumentation/Meetings/2019/11-27 last meeting]: |
| 58 | * **KL**: Liaise to develop concept for polishing. |
| 59 | |
| 60 | 2. Mechanical design/manufacture update: LC |
| 61 | |
| 62 | 3. Single-fibre/fibre-bundle test setup: HTL |
| 63 | |
| 64 | 4. Schedule revision discussion: All \\ |
| 65 | |
| 66 | 5. Spend: outstanding requirement: All \\ |
| 67 | |
| 68 | 6. Next steps: All \\ |
| 69 | |
| 70 | 7. DONM \\ |
| 71 | Wed. 11Dec19. |
| 72 | |
| 73 | 8. AoB \\ |
| 74 | |
| 75 | ---- |