Changes between Version 3 and Version 4 of Research/LhARA/DesignAndIntegration/Meetings/2023/2023-03-10


Ignore:
Timestamp:
Mar 16, 2023, 4:09:10 PM (21 months ago)
Author:
kurup
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/LhARA/DesignAndIntegration/Meetings/2023/2023-03-10

    v3 v4  
    99* Preparation of 6-month review document.
    1010* AOB
     11
     12== Actions ==
     13|| Actions      || Description  || Status
     14|| 22-12-06-04  || '''Chris Baker''' to provide a CAD model of the Gabor Lens test bench        ||  In progress
     15|| 22-12-06-05  || '''Clive Hill''' to import the CAD model into Creo to provide a better image of the Gabor Lenses.    ||  In progress
     16|| 23-01-17-02 || '''Ajit Kurup''' to get Dockerfiles for BDsim from Will.  || Closed
     17|| 23-01-17-03 || '''Ajit Kurup''' to investigate options for storing data somewhere easily accessible for the collaboration.  || In progress
     18|| 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress
     19
     20== Notes ==
     21Present:  Neil Bliss, Clive Hill, Ajit Kurup, Ken Long, Hywel Owen, Jaroslaw Pasternak, Will Shields, Colin Whyte\\
     22Apologies:  Rehanah  Razak
     23
     24        * Simulations, see slides from Will.
     25                * Tested emittance growth with just a drift.
     26                * GPT sampling in time and not using screens does not show the emittance growth.
     27                * No idea why using screens has this issue.
     28                * HO: Can contact people at LD who use GPT regularly to see if they can help.
     29                * HO posted a link to this article https://journals.aps.org/prab/abstract/10.1103/PhysRevSTAB.6.034202
     30                * NB: What are the details of the nozzle?
     31                        * 2.87mm is the exit aperture radius. Can increase this aperture to 4mm to improve transmission.
     32        * Document preparation.
     33                * NB circulated the pdf and has sent Hywel link to the Word
     34        * CAD, slides from Clive.
     35                * CAD of Gabor lens and target chamber for SCAPA.
     36                * A tape drive target has been added to the drawing.
     37                * The diagnostic camera behind the target requires a target to end flange distance of 130mm.
     38                * Discussion on the different vessels needed for the laser target.
     39                * HO gave some details of the EPAC target.
     40                * Discussion of details of the target region.
     41                * HO: Where does the waste laser go? This is an issue for EPAC.
     42                * A meeting with Ross and Chris should be arranged to discuss these details.
     43                       
     44        * AOB
     45                * Agreed to cancel the meeting next Tuesday as we will meet on Friday.