| 11 | |
| 12 | == Actions == |
| 13 | || 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress |
| 14 | |
| 15 | == Notes == |
| 16 | Present: Neil Bliss, Clive Hill, Ajit Kurup, Ken Long, Rehanah Razak, Colin Whyte, Will Shields \\ |
| 17 | Apologies: Hywel Owen, Jaroslaw Pasternak |
| 18 | |
| 19 | * Simulations. See slides from WS |
| 20 | * Preping IOP talk, see slides and give feedback. |
| 21 | * Emittance growth due to solenoids. |
| 22 | * Found a paper that looked at co-propagating an electron beam. |
| 23 | * Have a student working on CAD for outreach. |
| 24 | * CAD work - CH |
| 25 | * Working on parameterising the CAD model. |
| 26 | * Target chamber, looking at putting the final laser mirror on a translational stage. |
| 27 | * Looking at having a vertical plane laser configuration to provide better access in the target area. |
| 28 | |