= Design and Integration meeting: 08 August 2023 15:00 GMT = '''Zoom:''' https://ukri.zoom.us/j/99571436156 == Agenda == * Actions from last meeting. * Simulations. * Engineering. * AOB == Actions == || 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress || 23-07-25-01 || '''Neil, Clive, Colin''' Determine the thickness needed for the radiation shutter. || Closed == Notes == Present: Neil Bliss, Mark Johnson, Ajit Kurup, Ken Long, Jaroslaw Pasternak, Lilli Platt, Rehanah Razak, Will Shields, Colin Whyte\\ Apologies: Clive Hill, Hywel Owen * Actions * Update document. * CW: In progress. Goal is to have this done by the September collab meeting. May not include dose. * WS: Looking at dose calculation and should be able to include it. * Radiation. * NB: Contractor engaged, will start in Nov. Can think about using temporary wall instead of shutters but this does not provide the same flexibility. * No need to keep this action. * Simulations * Slides from WS. * Looking at the dose calculation done by HT Lau. * Slides from LP * Looking at optimising the octupole in stage 1. * Asymmetry in y is because the initial beam is asymmetric. * JP: Should look at using two octupoles to improve uniformity in y. * Discussion * Update from JP * Investigating FD doublet. Vertical tune then becomes very high. * Looking at FF doublet with very small second F. * NB: Update on engineering. * Vacuum modelling of the nozzle. Will have details to show next week. * FETS vacuum chamber. First pass FEA is done. * Meeting scheduled to discuss target vessel in Strathclyde. * Looking at adding detail to power consumption. * Updated schematic. * Shielding wall has now moved. * Need to agree the other elements in the beam line that will take up space, e.g. profile monitors, wall current monitors, etc. * Details of the cavity? * JP has looked at estimating the frequency of the first one. * AOB * KL: RR and KL working on simulation of the Lion beamline for proof of principle experiment. Will show some results soon. * JP: Is there an update on the BDSim workshop date. * Need a Doodle poll. * WS is design review and collab meeting on the same day? * KL: Yes.