Changes between Initial Version and Version 1 of Research/LhARA/ProjectBoard/Meetings/2024/01-23


Ignore:
Timestamp:
Jan 22, 2024 11:16:21 PM (4 months ago)
Author:
cwhyte1
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/LhARA/ProjectBoard/Meetings/2024/01-23

    v1 v1  
     1LhARA Project WPM Meeting 9th January 2024 14:00 GMT =
     2
     3Meeting URL: ​https://strath.zoom.us/j/84550543598?from=addon
     4
     5Meeting ID: 845 5054 3598 Password: 737274
     6
     7-------------------------------------------
     8
     9'''Agenda'''
     10
     11''PA1''
     12
     13Upcoming dates:
     14
     15 * WP5 consultation 3, Jan 24th Liverpool.  Tomorrow
     16
     17https://indico.stfc.ac.uk/event/923/?print=1
     18
     19 * WP6 LhARA/ISIS FFA meeting. Hardware R&D for the facilities.
     20
     21https://indico.stfc.ac.uk/event/933/.  Excellent meeting - magnets are challenging, RF less worrying
     22
     23
     24''PA2''
     25
     26Bridging funds - discussion
     27
     28Deliverables
     29Work Package 1. Project management: Deliverables
     30• D1 Early progress review CDR M6
     31• D2 Interim progress review CDR M12
     32• D3 Pre-CDR Review M18
     33• D4 CDR M24
     34
     35• D5 Pre-TDR review M30
     36• D6 TDR1 M36
     37• D7 Early progress review TDR2 M42
     38• D8 Interim progress review TDR2 M48
     39• D9 Pre-TDR2 review M54
     40• D10 TDR2 M60
     41Milestones
     42
     43Work package 2: Laser-driven proton and ion source
     44• M2.1: Prediction of optimised proton source parameters for 100+ TW laser systems based on hydrodynamic and kinetic simulations M12
     45• M2.2: First SCAPA ion source simulations and experiment completed M18
     46• M2.3: Report detailing optimisation of proton and ion generation on SCAPA, leading to LhARA laser
     47specification M30
     48• M2.4: Demonstration of 10 Hz operation of advanced targetry platform at ICL M48
     49• M2.5: Demonstration of stabilised 5 Hz beam generation on SCAPA M60
     50Work package 3: Proton and ion capture
     51• M3.1: Validate plasma simulations with existing Swansea experimental set-up M6
     52• M3.2: Progress report of large diameter plasma experiments and simulations M18
     53• M3.3: Next generation plasma lens testbench design M24
     54• M3.4: Progress report of standalone plasma apparatus build and commissioning M36
     55• M3.5: Progress report of large particle-number plasma experiments and simulations M48
     56• M3.6: Ion focussing results M60
     57• M3.7: Final plasma lens design M60
     58Work package 4: Ion-acoustic dose mapping
     59• M4.1: Geant4 simulations of beam energy deposition profile M18
     60• M4.2: Acoustic sensor array design M24
     61• M4.3: Iterative reconstruction methods M42
     62• M4.4: Integration: ultra-sonic array with radiobiology station M48
     63• M4.5: LhARA ion-acoustic test results M60
     64Work package 5: Novel end-station development
     65• M5.1: Design LhARA automated cell dish handling and environmental system M24
     66• M5.2: Report on end-station user-community consultation M24
     67• M5.3: Report on end-station component testing at Birmingham M24
     68• M5.4: Construct beam delivery room including end-station and cellular imaging capabilities M60
     69• M5.5: Specification of LhARA beam monitoring technology M24
     70• M5.6: Report on delivery of LhARA beam monitoring system M60
     71• M5.7: kGy/s tests at Birmingham M24
     72Work package 6: Design and integration
     73• M6.1: Final review of R&D work towards LhARA CDR M18
     74• M6.2: Final review of R&D work towards LhARA Phase 1 TDR M35
     75• M6.3: Final review of R&D work towards LhARA Phase 2 TDR M54
     76• M6.4: Technical report on FFA main magnet prototype M58.
     77• M6.5: Technical report on MA RF cavity prototype M58.
     78
     79
     80AOB