Changes between Version 2 and Version 3 of Research/DesignStudy/Meetings/2019-01-08-LARA


Ignore:
Timestamp:
Jan 9, 2019 11:20:09 AM (5 years ago)
Author:
longkr
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/DesignStudy/Meetings/2019-01-08-LARA

    v2 v3  
    3030== Notes: ==
    3131
    32 '''Present:'''
     32'''Present:''' JPo, CH, AK, KL, GB
    3333
    34 '''Apologies:'''
     34'''Apologies:''' JPa, OE
     35
     361. __Introduction: **//KL//**__
     37 * The five-yeara plan for MedAustron produced by MUW/TUW/MedAustron has the SmartPhantom work scheduled in.  The first exposure where we can be involved is October.  Need to be ready.  This places a spotlight on, e.g., the SmartPhanton preparations.
     38 * Some news from discussions before Christmas.  KL made a visit to GSI and discussed with colleagues there.  There are opportunities to expand our collaborative radiobiology activities.  In addition, GSI is organising a meeting on new directions in radiobiology, KL submitted an abstract to this just before Christmas.
     39 * We've submitted several other abstracts: AK ot PTCOG and JPa to IPAC.  We need to post these on the wiki.
     40 * Discussions with the Vice Dean indicate that we should prioritise drafting a i/p to the EPSRC call for 'Big Ideas'.  KL will draft and circulate for comment.
     41 * At these meetings (i.e. LARA CDR), KL proposed an increased emphasis on the h/w and prototyping projects (Gabor lens, SciWire and SmartPhantom).  This should go in parallel to the development of the CDR for LARA.
     421. __Notes on last meeting and actions arising: **//All//**__
     43 * **AK:** Prepare strawman SciWire schedule.
     44  * **Stands.**
     451. __Progress; comparison to schedule: **//AK//**__
     46 * AK requested spreadsheets from CH and KL so that he can produce the overview schedule (**action: KL, CH**).
     47 * SciWire/SmartPhantom update:
     48  * Showcase workshop will be 19Mar19 in SAF.  Need to invite people from low-energy ion-beam facilities and manufacturers.  All are invited to provide i/p to AK.
     49   * JPo volunteered: GSI: Peter Forck (Beam Diag) and Marco Durante. 
     50  * AK will prepare schedule to end of March; focus at the moment is on the jig for winding.
     51 * CDR:
     52  * KL is late with the completion of the introduction.  No one else is late (yet).
     53  * JPo/JPa had a discussion on the next steps.  Parameters have been agreed.  Risk mitigation possibilities for Gabor-lens failure have been considered.  Could use DC or pulsed solenoids, warm or SC, or HTSC.  Could be a project with Oxford Instruments. No technical reason to drive us to addopt SC/HTSC.
     54 * Gabor lens:
     55  * So far preparation conforms to the schedule.
     561. __Parameter table update for Gabor Lens and transport: **//KL//**__
     57 * Started to enter the parameters, then got pulled away.  Will be done asap.
     581. __Gabor lens recommissioning update: **//CH//**__
     59 * Lens is now in the conditioning phase. Vacuum pumping began early in December and continued over Christmas.  Pressure is still dropping slowly (has reached 2.9E-6mBar).
     60 * Strategy is to condition with HV/current and then add instrumentation.  A second round of leak checking will be performed when in the various stages of reassembly.
     61 * Radiation protection discussions have started.  X-ray emission needs to be quantified. 
     62 * Wish to do a visual inspection to seek explanation for small number of breakdowns during commissioning.
     63 * Paper on previous measurements in preparation.  Expect update on the document in the next weeks.
     641. __LARA CDR skeleton: update: **//All//**__
     65 * Noted above.  KL needs to finish introduction and then work shoudl begin on the more meaty sections.
     661. __Next steps:  **//All//**__
     67 * The preparation of a more detailed simulation of SmartPhantom is now important. Need to interface with HT.  Goal is to be complete for October.
     681. __AoB__
     69 * We agreed to meet fortnightly. 
    3570
    3671=== Summary of actions ===
    3772
     73* **AK:** Prepare strawman SciWire schedule.
     74* **KL, CH:** Send spreadsheet version of schedules for CDR preparation and Gabor Lens to AK.