Changes between Version 4 and Version 5 of Research/DesignStudy/Meetings/2019-02-19-LARA


Ignore:
Timestamp:
Feb 20, 2019 11:05:16 AM (5 years ago)
Author:
kurup
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/DesignStudy/Meetings/2019-02-19-LARA

    v4 v5  
    41411. __Progress; comparison to schedule: **//AK//**__\\
    4242 //SciWire:
    43   * Machining of winding rig nearly finished. About 3 weeks behind original (optimistic) schedule but still should be completed by end of March.
     43  * Machining of winding rig nearly finished. Only about 3 weeks behind the original (very optimistic) schedule made in November (this is thanks to the efforts of machine shop stepping in to replace Geoff).  The detector tests should still be completed by the end of March. Schedule should be updated to reflect these changes.
    4444 //Gabor lens:
    4545  * Hold up is rad safety paperwork