    41411. __Progress; comparison to schedule: **//AK//**__\\
    4242 //SciWire:
    43   * Machining of winding rig nearly finished. About 3 weeks behind original (optimistic) schedule but still should be completed by end of March.
     43  * Machining of winding rig nearly finished. Only about 3 weeks behind the original (very optimistic) schedule made in November (this is thanks to the efforts of machine shop stepping in to replace Geoff).  The detector tests should still be completed by the end of March. Schedule should be updated to reflect these changes.
    4444 //Gabor lens:
    4545  * Hold up is rad safety paperwork