Changes between Version 7 and Version 8 of Research/DesignStudy/Meetings/2019/07-25
- Timestamp:
- Jul 25, 2019, 10:41:46 AM (5 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
Research/DesignStudy/Meetings/2019/07-25
v7 v8 13 13 14 14 3. Layout, footprint, and infrastructure: JPo 15 * [raw-attachment:LhARA–CAD 15 * [raw-attachment:LhARA–CAD-SCHEME.pptx Slides] prepared by L.Clarke (RAL) in consultation with JPo were presented. Good progress on the outline of the footprint. 16 16 * We noted a number of issues; the transfer line into and out of the FFA, the size of the building, the absense of cavities in the ring. 17 17 * We also noted the absense of a shielding calculation. A guess of 0.5m shielding has been made (new [raw-attachment:LhARA–CAD-SCHEME-2.pptx slides] provided by LC after the meeting). Seemed to those present like an over estimate. Agreed we need a shielding calculation.