| 21 | |
| 22 | '''Notes''' |
| 23 | |
| 24 | '''KL''' : SG needs to be a separate entity - not dominated/driven by the Project Office. - All agreed to search for outside influence. '''AG''' and '''KL''' suggested names. |
| 25 | |
| 26 | '''CW:''' Some WPs are progressing very well but WP4 and WP5 are behind for good reasons. We need to provide help to them. I am happy with the progress of WP2, WP3 and there is confidence in WP6. We need to recognise where we are and suggest a new timetable that all WPs can follow. New timetable to be circulated later today. |
| 27 | |
| 28 | '''JP, KL''' : Dissemination plan - we need to reach out to relevant audiences. To discuss the next moves. |
| 29 | |
| 30 | '''DK''': to call/update WP1 meetings fortnightly. To check for LhARA Day meeting. To check for dates for Plenary meeting and circulate new timetable for proposal. |
| 31 | ---- |