    99An effort to develop a 'pre-CDR' has been initiated supported by the award of an STFC Opportunities 2019 award.  This page is being used to collect and share information in the preparation of the pre-CDR.
     10
     11----
     12
     13== Key dates ==
     14* **29Nov19**: First issue of the baseline. This will include the floor layout, WBS, Interfaces document and the parameter table.
     15* **31Dec19**: First end-to-end tracking simulation.
     16* **31/1/20**:
     17 - Design of the facility will be frozen.
     18 - First view of the costs.
     19 - R&D programme needed to realise LhARA and be able to write a technical design report will be defined.
     20* **28Feb20**: Complete the write-up of the pre-CDR.
     21* **Mar20**: External review of pre-CDR in advance of publication.
     22
     23----