     1'''WP5 meeting with the Project Office'''
     2
     3
     4''02 September 2021''
     5
     6TP – discussion with Carsten Welch (CaW )
     71.      Instrumentation in beam pipe – non intercepting unless beam moves off track. Gives you the beam info but does not measure what goes into the cells.
     81.      Gas profiler – 10 yrs work non-invasive, measurements with small e beam – can get 2d profile of beam as it passes detector. Minimal beam perturbation.
     9
     10Requirement is for pulse to pulse intensity only – remainder of beam system selects for energy and species, so only require intensity.
     11
     12Much of diagnostics for LhARA could be tested at Birmingham without vertical beamline.
     13•       Short pulses and small sizes requires money CaW happy to contribute from Cockroft but will need ‘leader’ to support students – 2PDRA for 2 years between Cockroft + BHam.
     14
     15Gas profiler – test, use with scaled down beam and then specify system for final implementation.
     16
     17Assume profiles are Ok – 2 x 1D profiles.
     182D profile needs TP silicon system – @ £0.5M.
     19
     20