| 1 | = WP6 meeting with the Project Office = |
| 2 | ''02 September 2021'' |
| 3 | WP6 JP & KL, CW |
| 4 | |
| 5 | JP kicker in bend to dump beam? – agree should be discussed for clinical system but does not yet need full design |
| 6 | Resources |
| 7 | Possible program would allow for CDR in phase1 (by end yr2) followed by TDR in yr3 with yr3 requiring 1FTE engineer. |
| 8 | |
| 9 | |
| 10 | • Gabor lens unlikely to converge in <2yrs. At high energy (clinical system) equivalent solenoids would need to be superconducting and would not be quickly tunable. Gabor lens in this situation offers significant advantages. |
| 11 | • May be possible to work with fixed first magnet and tune remaining components. |
| 12 | |
| 13 | |