WP6 meeting with the Project Office
02 September 2021 WP6 JP & KL, CW
JP kicker in bend to dump beam? – agree should be discussed for clinical system but does not yet need full design Resources Possible program would allow for CDR in phase1 (by end yr2) followed by TDR in yr3 with yr3 requiring 1FTE engineer.
- Gabor lens unlikely to converge in <2yrs. At high energy (clinical system) equivalent solenoids would need to be superconducting and would not be quickly tunable. Gabor lens in this situation offers significant advantages.
- May be possible to work with fixed first magnet and tune remaining components.