Changes between Version 1 and Version 2 of Research/DesignStudy/WPMGroup/Meetings/2021/09-02


Ignore:
Timestamp:
Sep 4, 2021 3:40:44 PM (3 years ago)
Author:
dkordopa
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/DesignStudy/WPMGroup/Meetings/2021/09-02

    v1 v2  
    1 = plenary meeting WPMs =
     1= one-to-one meetings with WPMs =
    22
    3 Test
     3WP2 – ND & KL, CW, DK
     4
     5The sub-team has weekly meetings. They have made a good progress with the costing and have started a risk registry.
     6
     7ND presented slides. Proposing to split the WP into 2 main themes: source demonstration/characterisation – lower risk /  R7D for full , stable, sustainable 10 Hz operation – higher risk.
     8[[span(style=color: #FF1000, KL- suggested to tackle the higher risk first. )]]
     9 
     10
     11Milestones have been identified:
     12
     13* MS1 Full 3D + hydro baseline simulations using optimised SCAPA-like conditions
     14* MS2 – Deliver  a diagnostic platform for proton and heavy ion beam characterisation
     15* MS3- perform baseline experiment for proton and carbon beams at 1 Hz using optimised conditions on SCAPA.
     16* MS4- conceptual design of sustainable target system complete
     17* MS5  completed concept design on ion source system
     18* MS6 continuous operation of ion source demonstrated
     19Costing:  It should be the Full Economic Cost . Capital costs will be organised through STFC.
     20Measurements in collaboration with Belfast. Belfast should be recognised.
     21[[span(style=color: #FF0000, KL suggested to add cost for people in Belfast as well as equipment cost. Maybe the additional cost for a student at Belfast? )]]
     22[[span(style=color: #FF0000, CW suggested to not underestimate Elisabetta's time on the costing sheet.)]]
     23
     24Action ND: to talk to people in Belfast wrt adding staff costing and studentship.
     25Action ND:  to send an updated costing sheet and the risk registry. - Done