    11= SmartPhantom meetings: Wednesday 13^th^ November 2019 =
     2
     3== Summary of actions: ==
     4 * **KL**: Liaise to develop concept for polishing.
     5 * **LC**: arrange packing of winding jig and inform HTL who will arrange transport.
    26
    37== Notes: ==
     
    591. Notes and actions from [wiki:Research/Instrumentation/Meetings/2019/11-06 last meeting]:
    610 * **KL**: Liaise to develop concept for polishing.
     11  * **Stands.**
    712 * **LC**: Complete detailed design of the boot.
     13  * **Done.** Reported below.
    814 * **HTL** will send summary simulations to indicate how close first SciFi layer must be to cell layer.
     15  * **Done.** Simulations had been circulated.
    916 * **AK**: Will send HTL the LabView code.
     17  * **Done.** HTL is working on the adaptation of the LabView code.
    1018 * **HTL**: Request thickness of culture flask window from MP.
     19  * **Done.** Thickness received from M.Puchalska.
    1120 * **LC**: arrange packing of winding jig and inform HTL who will arrange transport.
     21  * **Ongoing.**
    1222
    13232. Mechanical design/manufacture update: LC
     
    1727
    18283. Single-fibre test setup: HTL
     29 * Ready to go; revision of paperwork for use of source complete. 
     30 * Setting up for initial test with UV LED.
    1931
    20324. Schedule revision discussion: All \\
     33 * Schedue remains as posted previously.
    2134
    22355. Spend: outstanding requirement: All \\
     36 * No new spend identified.  Projected overspends identified and discussed with management at RAL and Imperial.
     37 * Need to quantify precisely.
    2338
    24396. Next steps: All \\
     40 * Execute single-fibre test with UV LED, work towards single fibre test with source.
     41 * Bring windin jig from RAL to Imperial.  Winding now urgent.
    2542
    26437. DONM \\
    27  * Next Wednesday.
     44 * Next Wednesday.  13:00 GMT.
    2845 
    29468. AoB \\
     47 * None.
    3048