Changes between Version 1 and Version 2 of Research/Instrumentation/Meetings/2020/01-08


Ignore:
Timestamp:
Jan 10, 2020, 1:14:16 PM (5 years ago)
Author:
longkr
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/Instrumentation/Meetings/2020/01-08

    v1 v2  
    16161. Notes and actions from [wiki:Research/Instrumentation/Meetings/2019/12-18 last meeting]:
    1717 * **KL**: Liaise to develop concept for polishing.
     18  * **Stands.**
    1819
    19 2. Mechanical design/manufacture update: LC
     202. Mechanical design/manufacture update: LC \\
     21 LC advises that there needs to be an improved transportation plan.  Some fibres were damaged in the potting.  However, the pig-tail has now been potted and can be collected from RAL.
    2022
    21 3. Single-fibre/fibre-bundle test setup: HTL
     23 HTL has produce a first clear-fibre light guide.
     24
     25 C/f machining will now be coordinated through Trevor Savidge.  Hope to move this along as it is the holding item for progress now that first light-guide has been produced by HTL.
     26
     273. Single-fibre/fibre-bundle test setup: HTL \\
     28 Pig tail will be returned from RAL to Imperial so that work on it can start next week.  Will require polishing and then check of light production.  Antonin has offered to measure the light production using his spectrophotometer. \\
    2229
    23304. Schedule revision discussion: All \\
     31 No update.
    2432
    25335. Spend: outstanding requirement: All \\
     34 No update.
    2635
    27366. Next steps: All \\
     37 Return pig tail to Imperial and begin tests.  In parallel need to make advance manufacture of frames.
    2838 
    29397. DONM \\