Version 2 (modified by 21 months ago) ( diff ) | ,
---|
Design and Integration meeting: 7 March 2023 15:00 GMT
Zoom: https://ukri.zoom.us/j/99571436156
Agenda
- Actions from last meeting.
- Simulations.
- AOB
Actions
Actions | Description | Status |
22-12-06-04 | Chris Baker to provide a CAD model of the Gabor Lens test bench | In progress |
22-12-06-05 | Clive Hill to import the CAD model into Creo to provide a better image of the Gabor Lenses. | In progress |
23-01-17-02 | Ajit Kurup to get Dockerfiles for BDsim from Will. | Closed |
23-01-17-03 | Ajit Kurup to investigate options for storing data somewhere easily accessible for the collaboration. | In progress |
23-01-24-01 | All to prepare document for the milestone to update the baseline | In progress |
Notes
Present: Neil Bliss, Clive Hill, Ajit Kurup, Ken Long, Hywel Owen, Rehanah Razak, Will Shields
Apologies: Jaroslaw Pasternak, Colin Whyte
- Document for the 6-month review.
- NB is preparing a section on the facility layout and has written a first draft.
- AK: Would it be useful to include some details on the plan to address sustainability?
- NB can add some details based on the work done for the CALA facility in Munich.
- Discussion.
- WS is getting plots together for the document, text will follow.
- Discussion on the different configurations to be mentioned in the report.
- CAD
- NB has had discussions with Chris Baker and now has the CAD model of the lens.
- CW will upload a drawing of the SCAPA target area, which will be updated with details of the tape target.
- These can then be put together to present in the report.
- CH showed the CAD model.
- NB has had discussions with Chris Baker and now has the CAD model of the lens.
- AK: Will there be any input from the vacuum group at DL.
- NB: DL will wait for the CAD model to be ready before doing any calculations.
- NB: If there is time we could add a bit on the general vacuum design (i.e. how the design of the facility segregates the vacuum system into sections).
- KL: Rehanah will use BDSIM to look at the delivery into the end stations to produce different spot sizes, micro-beams, etc.
- AK: Was looking into getting the BDSIM Docker image running.
- Discussion on how best to run BDSIM.
- Agreed using the version on CVMFS (available through the linux cluster)is simplest. Using Docker can be looked at in the future if there is a strong need for it.
- AK: Was looking into getting the BDSIM Docker image running.
- NB to add more detail to the infrastructure section and Hywel will add to the Overleaf when it's ready.
- Sections
- Infrastructure
- Design and simulations
- AK: Should we add a section on the RF? We can outline the key parameters and the technology choices being considered.
- Discussion.
- AK to outline current technology choices.
- AK to add subsection headings to document.