| | 11 | |
| | 12 | == Actions == |
| | 13 | || Actions || Description || Status |
| | 14 | || 22-12-06-04 || '''Chris Baker''' to provide a CAD model of the Gabor Lens test bench || In progress |
| | 15 | || 22-12-06-05 || '''Clive Hill''' to import the CAD model into Creo to provide a better image of the Gabor Lenses. || In progress |
| | 16 | || 23-01-17-03 || '''Ajit Kurup''' to investigate options for storing data somewhere easily accessible for the collaboration. || In progress |
| | 17 | || 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress |
| | 18 | |
| | 19 | == Notes == |
| | 20 | Present: Neil Bliss, Clive Hill, Ajit Kurup, Jaroslaw Pasternak, Rehanah Razak, Will Shields, Colin Whyte\\ |
| | 21 | Apologies: Ken Long, Hywel Owen |
| | 22 | * Slides from Will |
| | 23 | * Reoptimising for the SCAPA beam with new values using tout in GPT. |
| | 24 | * Solution for beta=50m, work in progress |
| | 25 | * Discussion. |
| | 26 | * Should include this result in the report but state this is work in progress. |
| | 27 | * Discussion on talks at the review. |
| | 28 | * JP might be able to make the meeting in person. |
| | 29 | * NB has a talk on infrastructure. |
| | 30 | * Slides from Clive on the CAD layout. |
| | 31 | * Target chamber layout. |
| | 32 | * Discussion on the need to move the nozzle and whether the camera should be normal to the target. |
| | 33 | * Need to discuss with Ross and Chris. |
| | 34 | * NB: Should the image of the target and camera be included in the presentation? |
| | 35 | * Discussion: |
| | 36 | * Agreed that it would be useful to include the image to highlight the issues that need to be addressed. |
| | 37 | * NB went through the section on infrastructure in the 6-month review document. |
| | 38 | * WS went through the section on the design. |
| | 39 | * AOB |
| | 40 | * No meeting next Tuesday as it's the review. |
| | 41 | |