    v1 v2  
    99* Preparation of 6-month review document.
    1010* AOB
     11
     12== Actions ==
     13|| Actions      || Description  || Status
     14|| 22-12-06-04  || '''Chris Baker''' to provide a CAD model of the Gabor Lens test bench        ||  In progress
     15|| 22-12-06-05  || '''Clive Hill''' to import the CAD model into Creo to provide a better image of the Gabor Lenses.    ||  In progress
     16|| 23-01-17-03 || '''Ajit Kurup''' to investigate options for storing data somewhere easily accessible for the collaboration.  || In progress
     17|| 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress
     18
     19== Notes ==
     20Present:  Neil Bliss, Clive Hill, Ajit Kurup, Jaroslaw Pasternak, Rehanah  Razak, Will Shields, Colin Whyte\\
     21Apologies:  Ken Long, Hywel Owen
     22        * Slides from Will
     23                * Reoptimising for the SCAPA beam with new values using tout in GPT.
     24                * Solution for beta=50m, work in progress
     25                        * Discussion.
     26                        * Should include this result in the report but state this is work in progress.
     27        * Discussion on talks at the review.
     28                * JP might be able to make the meeting in person.
     29                * NB has a talk on infrastructure.
     30        * Slides from Clive on the CAD layout.
     31                * Target chamber layout.
     32                        * Discussion on the need to move the nozzle and whether the camera should be normal to the target.
     33                        * Need to discuss with Ross and Chris.
     34                * NB: Should the image of the target and camera be included in the presentation?
     35                        * Discussion:
     36                                * Agreed that it would be useful to include the image to highlight the issues that need to be addressed.
     37        * NB went through the section on infrastructure in the 6-month review document.
     38        * WS went through the section on the design.
     39        * AOB
     40                * No meeting next Tuesday as it's the review.
     41