| | 11 | |
| | 12 | == Actions == |
| | 13 | || 23-01-24-01 || '''All''' to prepare document for the milestone to update the baseline || In progress |
| | 14 | |
| | 15 | == Notes == |
| | 16 | Present: Clive Hill, Ajit Kurup, Ken Long, Jaroslaw Pasternak, Lilli Platt, Rehanah Razak, Colin Whyte, Will Shields\\ |
| | 17 | Apologies: Neil Bliss, Hywel Owen |
| | 18 | * CAD - CH |
| | 19 | * CH showed images of the design of the target chamber to allow for moveable mirrors and the camera. |
| | 20 | * Layout of the 7 gabor lens capture section adding in vacuum valves. |
| | 21 | * Discussion of the space between Gabor lenses 2 and 3 and the space for the shielding wall. |
| | 22 | * Discussion of the thickness of the radiation shutter and absorption of neutrons. |
| | 23 | * Action: Determine the thickness needed for the radiation shutter. |
| | 24 | * Simulations. |
| | 25 | * Slides from JP: |
| | 26 | * Search for parameters for the doublet lattice. |
| | 27 | * Found tune per cell to give the same as the old working point. |
| | 28 | * Slides from WS: |
| | 29 | * Using down-sampled SCAPA beam. |
| | 30 | * Spot size optimisation. |
| | 31 | * FFA injection conditions. |
| | 32 | * Meeting with CERN. |
| | 33 | * BDSIM interface to RF-Track and xsuite. |