Design and Integration meeting: 07 May 2024 15:00 GMT
Zoom: https://ukri.zoom.us/j/99571436156
Agenda
- Milestone Report
- Simulations.
- Engineering.
- AOB
Actions
Notes
Present: Clive Hill, Mark Johnson, Ta-Jen Kuo, Ajit Kurup, Hywel Owen, Matt Pereira, Will Shields, Colin Whyte
Apologies: Andy Goulden, Ken Long, Jaroslaw Pasternak, Rehanah Razak
- Milestone report
- Just need to transfer the milestone report to the 18th month.
- HO: need to add the drawing of the cavity.
- CH to check the CAD file.
- Simulation
- WS:
- Working on the IPAC paper
- Looking at beam size in the injection line.
- Discussion regarding size of the beam, dispersion and beam distribution.
- TJK:
- Field clamp design.
- Looked at attaching the clamp to the yoke.
- WS:
- Engineering - CH
- Showed the cavity CAD models. Ferrite won't fit as it is. MA should
- Looking at injection line.
- Need details of the septum. Looked at the EMMA design.
- Space constraint for the septum and the large injection angle. There is space for a magnet 450mm wide.
- AOB