wiki:Research/LhARA/DesignAndIntegration/Meetings/2024/2024-05-07

Design and Integration meeting: 07 May 2024 15:00 GMT

Zoom: https://ukri.zoom.us/j/99571436156

Agenda

  • Milestone Report
  • Simulations.
  • Engineering.
  • AOB

Actions

Notes

Present: Clive Hill, Mark Johnson, Ta-Jen Kuo, Ajit Kurup, Hywel Owen, Matt Pereira, Will Shields, Colin Whyte
Apologies: Andy Goulden, Ken Long, Jaroslaw Pasternak, Rehanah Razak

  • Milestone report
    • Just need to transfer the milestone report to the 18th month.
    • HO: need to add the drawing of the cavity.
      • CH to check the CAD file.
  • Simulation
    • WS:
      • Working on the IPAC paper
      • Looking at beam size in the injection line.
        • Discussion regarding size of the beam, dispersion and beam distribution.
    • TJK:
      • Field clamp design.
      • Looked at attaching the clamp to the yoke.
  • Engineering - CH
    • Showed the cavity CAD models. Ferrite won't fit as it is. MA should
    • Looking at injection line.
      • Need details of the septum. Looked at the EMMA design.
      • Space constraint for the septum and the large injection angle. There is space for a magnet 450mm wide.
  • AOB
Last modified 7 months ago Last modified on May 14, 2024, 11:59:23 AM

Attachments (1)

Download all attachments as: .zip

Note: See TracWiki for help on using the wiki.