| | 11 | |
| | 12 | == Actions == |
| | 13 | |
| | 14 | == Notes == |
| | 15 | Present: Clive Hill, Ta-Jen Kuo, Ajit Kurup, Hywel Owen, Jaroslaw Pasternak, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\ |
| | 16 | Apologies: Andy Goulden, Mark Johnson, Ken Long, |
| | 17 | |
| | 18 | * Final report |
| | 19 | * Collab meeting in beginning of Sept. Aim is to have the report ready for then for discussion. |
| | 20 | * High-energy line. |
| | 21 | * JP: Optics design exists. |
| | 22 | * CH: Details of this is needed. |
| | 23 | * WS: Working on this and will send details to CH soon. |
| | 24 | * JP: Waiting for trackable field map of the FFA and can then finalise the transfer line and injection. |
| | 25 | * Engineering - CH |
| | 26 | * Slides from last week on the injection line. |
| | 27 | * Need details of the kicker |
| | 28 | * Sketching the coils of the LhARA magnet in CAD (similar to what was done for the FETS-FFA magnet). |
| | 29 | * Showed details from Emi's presentation on diagnostics to see how we could use this for LhARA. |
| | 30 | * Potential issue with the length of the BPM and wall current monitor. |
| | 31 | * JP: diagnostics will have to be inclined to make them fit. |
| | 32 | * Simulations |
| | 33 | * TJK showed slides on the magnet yoke and clamp optimisation. |
| | 34 | * WS: working on injection line. |
| | 35 | * AOB |
| | 36 | |