Changes between Version 2 and Version 3 of Research/LhARA/DesignAndIntegration/Meetings/2024/2024-06-25


Ignore:
Timestamp:
Jul 2, 2024, 11:30:49 AM (17 hours ago)
Author:
kurup
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/LhARA/DesignAndIntegration/Meetings/2024/2024-06-25

    v2 v3  
    99* Simulations.
    1010* AOB
     11
     12== Actions ==
     13
     14== Notes ==
     15Present:    Clive Hill, Ta-Jen Kuo, Ajit Kurup,  Hywel Owen, Jaroslaw Pasternak, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\
     16Apologies:  Andy Goulden, Mark Johnson, Ken Long,   
     17
     18        * Final report
     19                * Collab meeting in beginning of Sept. Aim is to have the report ready for then for discussion.
     20                * High-energy line.
     21                        * JP: Optics design exists.
     22                        * CH: Details of this is needed.
     23                        * WS: Working on this and will send details to CH soon.
     24                * JP: Waiting for trackable field map of the FFA and can then finalise the transfer line and injection.
     25        * Engineering - CH
     26                * Slides from last week on the injection line.
     27                        * Need details of the kicker
     28                * Sketching the coils of the LhARA magnet in CAD (similar to what was done for the FETS-FFA magnet).
     29                * Showed details from Emi's presentation on diagnostics to see how we could use this for LhARA.
     30                        * Potential issue with the length of the BPM and wall current monitor.
     31                        * JP: diagnostics will have to be inclined to make them fit.
     32        * Simulations
     33                * TJK showed slides on the magnet yoke and clamp optimisation.
     34                * WS: working on injection line.
     35        * AOB
     36