| 13 | == Notes == |
| 14 | Present: Clive Hill, Ta-Jen Kuo, Ajit Kurup, Ken Long, Hywel Owen, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\ |
| 15 | Apologies: Andy Goulden, Mark Johnson, Jaroslaw Pasternak |
| 16 | |
| 17 | * Engineering |
| 18 | * CH showed slides on engineering issues to be addressed. |
| 19 | * Discussed some of these issues. |
| 20 | * Agreed to fix the circumference of the ring and magnet layout. |
| 21 | * Agreed to write down outstanding issues, the implications of these and options for addressing these in the CDR. |
| 22 | |
| 23 | * Simulations |
| 24 | * TJK showed slides on tracking simulations using the code FixedField and the field map produced by Opera. |
| 25 | |
| 26 | * AOB |
| 27 | * CDR |
| 28 | * HO showed the outline of the CDR in Overleaf |
| 29 | * Discussed how to prepare the content. |
| 30 | * AK: Is there a date agreed for the design to be frozen? |