  • Research/LhARA/DesignAndIntegration/Meetings/2024/2024-09-17

    v1 v2  
    88* Simulations.
    99* AOB
     10
     11== Actions ==
     12
     13== Notes ==
     14Present: Clive Hill, Ta-Jen Kuo, Ajit Kurup, Ken Long, Hywel Owen, Jaroslaw Pasternak, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\
     15Apologies:   \\
     16
     17        * Engineering
     18                * CH: discussion of the direction of the engineering work.
     19                * JP showed a schematic of new ring design and new injection and extraction scheme with parameters.
     20                * Discussion of the work to be presented in the CDR, plan for future work on the FFA and the option for having a review of the ring design in a few months' time.
     21        * CDR preparation update from WS
     22                * Conversation about the laser parameters have changed.
     23                        * Spectrum has now changed and has much a higher cut-off.
     24                        * KL: this is work in progress and will require a few more iterations.
     25        * Simulations
     26                * RR:
     27                        * Update on the final focus in the end station.
     28                        * Thinking of moving the upstream octupole to the end station beam line.
     29                * MP
     30                        * Optics update.
     31                        * Found the cause of needing to use a SigmaE correction factor of 0.006 is due to an issue with MADX.
     32        * AOB