| | 14 | - WP2: continued progress. |
| | 15 | - Team presently analysing results of recent experiments. Also have made some simulations while waiting for the Lancaster recruitment. |
| | 16 | - Lancaster postdoc expected in post soon. This should strengthen the simulation effort. |
| | 17 | - WP3: now progressing recruitment of post-doc effort. |
| | 18 | - Additional effort brought onto project. Post-doc expected in post at the start of September. |
| | 19 | - WP4: continued progress. |
| | 20 | - First test of camera with fluorescent dye successful. Now calibrating various aspects. Design of PoP experiment progressing. |
| | 21 | - WP5: progress. |
| | 22 | - Documentation of most recent consultation meeting not complete. Also, solicitation of suggestions of types of experiment not yet sent out. Some encouragement of team may be necessary. |
| | 23 | - WP6: continued progress. |
| | 24 | - Updates to FFA design being discussed. Simulation of Stage 1 at an advanced stage, presently considering octopoles. Engineering progressing too, design for target chamber now quite detailed. Engineering of building etc. being advanced. |
| | 25 | - Update to stage 1 lattice will be done without renewed dose calculation. Issue is that code used for pre-CDR was can not be recovered. |
| | 26 | - WP0: Changes of personnel: K.Kirkby and N.Bliss have/will retire. Discussion of how to proceed in WP0 meeting not always consistent with |
| | 35 | - Strong comment from CJ, **adopted**, present project consistently as "LhARA to serve ITRF". Implies change in title, for example. |
| | 36 | - Issue of collaboration's identity discussed. **Agreed** that resolution of the apparent tension is likely to be that the "LhARA initiative", which is a "programme", is the function of the collaboration. One of the three key pillars of this is the "LhARA/ITRF project". The discussion of the LhARA/ITRF project is then consistent with a single integrated project. |
| | 37 | - Concrete changes to present doc; |
| | 38 | - Change title to "The integrated PA2 project plan to develop LhARA to serve the ITRF". |
| | 39 | - Drop content of PM section of annex awaiting comment.\\ |