Changes between Version 4 and Version 5 of Research/LhARA/ProjectBoard/Meetings/2024/02-20


Ignore:
Timestamp:
Feb 20, 2024 1:12:07 PM (3 months ago)
Author:
cwhyte1
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/LhARA/ProjectBoard/Meetings/2024/02-20

    v4 v5  
    2020
    2121
    22 Deliverables
    23 Work Package 1. Project management: Deliverables
    24 
    25 • ''' D5 Initial progress review TDR & technical de-risk update M30 '''
    26 • ''' D6 Interim progress review TDR & technical de-risk update M36 '''
    27 • ''' D7 Final progress review TDR & technical de-risk update M42 '''
    28 • ''' D8 Stage 1 TDR & technical de-risk report M48 '''
    29 
    3022Milestones
    31 
    32 Work package 2: Laser-driven proton and ion source
    33 
    34 • ''' M2.3: Investigation and demonstration of 10 Hz debris and damage challenges at ICL M36 '''
    35 • ''' M2.4: Demonstration of continuous operation of 1 Hz beam generation on SCAPA M48 '''
    36 
    37 Work package 3: Proton and ion capture
    38 
    39 • ''' M3.3: Progress report on increased voltage penning trap simulations and operation. M36 '''
    40 • ''' M3.4: Final report high voltage penning trap operation. M48 '''
    4123
    4224=== Radiobiological Science and technology
     
    6042 • ''' M5.6: Report on LhARA stage 1 beam monitoring system M48. '''
    6143
     44Plus numerical studies to interpret ans evaluate experimental programme - Student led.
    6245
    63 Work package 6: Design and integration
     46=== ITRF/LhARA Facility R&D
     47
     48Stage. 1 TDR
     49
     50Work package 2: Laser-driven proton and ion source
     51
     52• ''' M2.3: Investigation and demonstration of 10 Hz debris and damage challenges at ICL M36 '''
     53• ''' M2.4: Demonstration of continuous operation of 1 Hz beam generation on SCAPA M48 '''
     54
     55Work package 3: Proton and ion capture
     56
     57• ''' M3.3: Progress report on increased voltage penning trap simulations and operation. M36 '''
     58• ''' M3.4: Final report high voltage penning trap operation. M48 '''
     59
     60
     61Work package 0 & 6: Design and integration
    6462
    6563• ''' M6.2: Final review of R&D work towards LhARA Phase 1 TDR M42 '''
    66 • ''' M6.3: Review of R&D work towards LhARA Phase 2 TDR M48 '''
     64
     65Stage 2 CDR 
     66• ''' M6.3: Review of R&D work towards LhARA Phase 2 CDR M48 '''
     67
     68
     69=== Management ===
     70
     71Work Package 0 & 1. Project management: Deliverables plus internationalisation
     72
     73• ''' D5 Initial progress review TDR & technical de-risk update M30 '''
     74• ''' D6 Interim progress review TDR & technical de-risk update M36 '''
     75• ''' D7 Final progress review TDR & technical de-risk update M42 '''
     76• ''' D8 Stage 1 TDR & technical de-risk report M48 '''
    6777
    6878Work Package 8: