     1= LhARA Radiobiology Meeting: 20Aug26; 14:00 BST =
     2
     3**ZOOM:** https://imperial-ac-uk.zoom.us/j/98220889714?pwd=SM90vOF7BKSXoU3mD9q7OwBQo4IVB3.1
     4
     5- Planning Document: https://docs.google.com/document/d/1OTARVtxhLRu02S6CLdRDB2QlGvCqDfZ3aWBifjIFs_Q/edit?tab=t.0
     6
     7- Trello: https://trello.com/invite/b/67587c515b0c69656ee78b48/ATTIe86f94b24e3e5884e4cb87e5ed3b89ab64321B83/poplar
     8
     9== Meeting Agenda ==
     10
     111. Beamline Simulation
     12 - Josie: Characterisation of ELI and SCAPA sources
     13 - Josie: Simulations of a dipole at SCAPA
     14
     152. Instrumentation
     16 - Fast Electrons
     17  - Richard H.: Findings since last meeting
     18 - RCF
     19  - Update from NPL
     20  - Mark has found some EBT4 delaminated: https://www.ashland.com/industries/medical/radiotherapy-films/ebt4
     21 - Air Scintillation
     22  - Colin/Narendar: Planning to meet to discuss the feasibility of the implementation at SCAPA and the timeframe
     23
     243. BioPrep
     25 - Notes from meeting with Alexander Mullen
     26  - Vertical beam needed?
     27
     284. SCAPA
     29 - Updates
     30
     315. Review Trello: https://trello.com/invite/b/67587c515b0c69656ee78b48/ATTIe86f94b24e3e5884e4cb87e5ed3b89ab64321B83/poplar
     32
     336. DoNM
     34 - 03/09/26
     35
     367. AoB
     37
     38=== Summary of actions required ===
     39
     40In-Beam Diagnostics
     41- **Unassigned**: Acquire a glass sheet
     42- **Unassigned**: Get a new RCF batch and calibrate
     43- **TP**: Testing delaminating EBT3
     44- **PH**: Obtain transparent fibre or an alternative method for light transport
     45- **PH**: Obtain a lens for hollow fibre tests
     46- **CD**: Simulate energy deposited in transport fibres
     47- **KL, CD, JMcG, PH**: Design a system to make full scifi prototypes
     48- **KL, CD, JMcG, PH**: Make a full scifi prototype
     49- **KL, CD**: Send clear fibre to SCAPA before 16th August (Contact Ewan or Colin since Robbie is USA)
     50- **KL, CD, JMcG, PH**: Discuss visit to Birmingham to test SciFi
     51- **RW, CD**: Study the correlation between laser diagnostics and mean dose
     52- **Unassigned**: Investigate how a phosphor sheet could be incorporated into the design of the cell dish
     53- **CW**: Investigate the feasibility of ICTs for our beamline
     54- **MH**: Investigate LET detector
     55- **CW**: Ask Narender about air fluorescence implementation
     56- **JMcG**: Investigate using IF as a dosimeter
     57
     58
     59Bio Next Steps
     60- **EM, CD, JMcG**: Write up technical summary of Phase 2
     61- **EM**: Write up a biology plan for a 2 PMQ setup
     62- **Unassigned**: Obtain an inverted microscope
     63- **Unassigned**: Obtain multi-chamber haemocytometers (Might be able to use Birmingham's)
     64- **Unassigned**: Obtain a thermostat for the incubator
     65- **EM**: Run controls to examine how long the cells can survive vertically
     66- **JMcG**: Plan a test of vertical cell survival using Emma/Jason's HeLa cell line and Marie's cell line
     67- **JMcG**: Produce a HeLa colony that can survive on Mylar
     68
     69Beamline Modelling
     70- **Unassigned**: Investigate how to improve the beamline beyond CV=8%
     71- **CD**: Examine energy spectra variation
     72- **RW, CD**: Source characterisation
     73
     74Alternate Beamlines
     75- **JMcG**: Simulate BELLA
     76- **JMcG**: Simulate ELI
     77