29 | | Present: |
| 29 | Present: Chris Hunt, HT Lau, Will Shields, Ajit |
| 30 | |
| 31 | • HT - busy commissioning carbon beam. |
| 32 | • Finalised carbon beam spot sizes in research room (room 1). |
| 33 | • Issue in BDSIM using carbon beams. WS will look into it. |
| 34 | • Got good comparison with protons at 800MeV comparing BDSIM and beam profile measurements. 120MeV-400MeV/nucleon carbon measurements were way off. |
| 35 | • May be issue with the physics options. |
| 36 | • Chris - Gabor lens update. |
| 37 | • Paperwork for Radiation source nearly there. |
| 38 | • Camera good but issues with getting it to work with the laptop. |
| 39 | • Aim to have source installed next week. |
| 40 | • Will |
| 41 | • Need input from Claire or Ruth on cliniac geometries. |
| 42 | • IPAC stuff. |
| 43 | • IBA development on dosimetry. |
| 44 | ○ Comparing voxelised simulations with dosimetry measurements. |
| 45 | • AK - SciWire |
| 46 | • SciWire construction started. |
| 47 | • Low-energy beam diagnostics workshop last week was a success, with some interesting talks and discussions and a tour of the Gabor lens and laser facility and a few posters. |
| 48 | • Also in the middle of dealing with the paperwork for the testing with the Sr-90 source. |