Changes between Version 1 and Version 2 of Research/SimulationExperiment/Meetings/2019-10-15


Ignore:
Timestamp:
Oct 15, 2019 8:34:11 PM (4 years ago)
Author:
kurup
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/SimulationExperiment/Meetings/2019-10-15

    v1 v2  
    2828
    2929== Notes ==
    30 Present:
     30Present: HT, Juergen, Will, Ajit
     31
     32        * Gabor lens - JPo
     33                * Lens is disassembled.
     34                * Currently doing modification drawings to the lens before it is re-assembled.
     35                * Pump repair will cost £4k
     36                        * Bearings damaged.
     37                       
     38        * SciWire - AK
     39                * Source tests did not produced scintillation light. Rate from the source was much less than expected.
     40                * Could test with collimated torch to investigate cross-talk.
     41                * Tests now concluded as lab space is needed for the SmartPhantom.
     42        * SmartPhantom - HT
     43                * Discussing the aperture and frame thicknesses. Smaller aperture prototype resolved warping but aperture is a bit too small.
     44                * Test to illuminate a single fibre longitudinally.
     45                        * Test optics, readout and image processing software.
     46        * Round table - Will
     47                * Can spend more time on CCAP work.
     48                * BDSIM can't do injection and extraction.
     49                * Collating a list of things needed for the simulation.
     50                * FFA ring, need to think about how to implement the magnetic field.
     51                * Variable frequency cavities.
     52                        * Could use a field map, have a 4D interpolator.
     53                * Space charge: can look at a simple component with and without space charge.
     54        * AOB
     55                * New server
     56                        * Nearly ready just waiting for the domain to be assigned.
     57                        * JPo: ICT installed software and licenses on previous server.
     58                        * Install Inventor.
     59                * Imperial account for Will