| 30 | | Present: |
| | 30 | Present: HT, Juergen, Will, Ajit |
| | 31 | |
| | 32 | * Gabor lens - JPo |
| | 33 | * Lens is disassembled. |
| | 34 | * Currently doing modification drawings to the lens before it is re-assembled. |
| | 35 | * Pump repair will cost £4k |
| | 36 | * Bearings damaged. |
| | 37 | |
| | 38 | * SciWire - AK |
| | 39 | * Source tests did not produced scintillation light. Rate from the source was much less than expected. |
| | 40 | * Could test with collimated torch to investigate cross-talk. |
| | 41 | * Tests now concluded as lab space is needed for the SmartPhantom. |
| | 42 | * SmartPhantom - HT |
| | 43 | * Discussing the aperture and frame thicknesses. Smaller aperture prototype resolved warping but aperture is a bit too small. |
| | 44 | * Test to illuminate a single fibre longitudinally. |
| | 45 | * Test optics, readout and image processing software. |
| | 46 | * Round table - Will |
| | 47 | * Can spend more time on CCAP work. |
| | 48 | * BDSIM can't do injection and extraction. |
| | 49 | * Collating a list of things needed for the simulation. |
| | 50 | * FFA ring, need to think about how to implement the magnetic field. |
| | 51 | * Variable frequency cavities. |
| | 52 | * Could use a field map, have a 4D interpolator. |
| | 53 | * Space charge: can look at a simple component with and without space charge. |
| | 54 | * AOB |
| | 55 | * New server |
| | 56 | * Nearly ready just waiting for the domain to be assigned. |
| | 57 | * JPo: ICT installed software and licenses on previous server. |
| | 58 | * Install Inventor. |
| | 59 | * Imperial account for Will |