LhARA pre-CDR Meeting 18th Feb 2020
Meeting details
14:00 Room 532, Blackett Lab.
Zoom details:
Join Zoom Meeting https://ukri.zoom.us/j/865262978
Phone one-tap: United Kingdom: +442034815237,,865262978# or +442039663809,,865262978#
Join by Telephone For higher quality, dial a number based on your current location.
United Kingdom:
+44 203 481 5237
+44 203 966 3809
+44 131 460 1196
+44 203 051 2874 0800 031 5717Meeting ID: 865 262 978
Join from an H.323/SIP room system H.323: 162.255.37.11 (US West) 162.255.36.11 (US East) 221.122.88.195 (China) 115.114.131.7 (India) 213.19.144.110 (EMEA) 103.122.166.55 (Australia) 209.9.211.110 (Hong Kong) 64.211.144.160 (Brazil) 69.174.57.160 (Canada) 207.226.132.110 (Japan) Meeting ID: 865 262 978
International numbers https://ukri.zoom.us/u/ap9aBI2Eh
SIP: 865262978@…
Skype for Business (Lync) https://ukri.zoom.us/skype/865262978
Skype on a SurfaceHub SIP: 865262978@… https://ukri.zoom.us/skype/865262978
Agenda
- Action items from last meeting.
- JPas to send AK beta and alpha as a function of S (calculated by BeamOptics).
- System updates.
- Laser driven proton and ion source.
- Proton and ion capture.
- Stage 1 beam transport: Beam transport and delivery to the in vitro end station.
- Stage 2 beam transport: Post-acceleration and beam delivery to the in vivo end station.
- Biological end stations.
- Infrastructure and Integration.
- Project plan for the delivery of LhARA.
- Safety.
- End-to-end simulation.
- Instrumentation.
- R&D plan and schedule.
- Writing the pre-CDR.
- A.O.B.
Notes
Participants: AK, GA, JPar, HTL, WS, KL, JMat
Apologies: JPas
- Action items
- JPas to send AK beta and alpha as a function of S (calculated by BeamOptics).
- Stands
- JPas to send AK beta and alpha as a function of S (calculated by BeamOptics).
- System updates
- Laser
- AK to arrange meeting to discuss R&D plan and write up.
- Capture
- Meeting on Friday with Colin and KL to discuss R&D plan.
- KL: Arranging meeting to coordinate the work.
- Beam transport
- WS: Updating Stage 1 design to get alpha to 0.
- Couldn't find solution.
- Lattice CCAP-v5 gives an elliptical beam in the end station.
- Looked at updating previous lattices.
- Using octopole after lens 5 (which now must be a solenoid) gives a more uniform distribution.
- AK to arrange meeting to discuss writing up.
- HTL:
- JPas looked at HTL's design in BeamOptics. Beta was getting very small in places.
- Looking for new solution to avoid this. Found minimum beta of about 1cm but this may still have problems with space charge.
- HTL to look at simulating this using GPT.
- WS: Updating Stage 1 design to get alpha to 0.
- End stations - JPar
- Waiting on finalising the beam line before updating floor plan.
- Discussed R&D plan. For the end stations that is automation of placing samples in the beam line.
- Collaboration with Birmingham. Currently looking for space to build lab there.
- Will do preliminary flash research in the next few weeks
- Kristoffer Petersson, now at Oxford was Lausanne, working on FLASH. Look to collaborate. They have a flash electron machine, which would complement our protons.
- Will hopefully go to Manchester on the 5th March.
- Infrastructure and integration - GA
- Updates to layout waiting on design being finalised.
- Started writing.
- Spoke to CLF. Have a paragraph on safety from them. References to existing lasers. Other issues will be solved with EPAC.
- CLF mentioned shielding should be between target and laser room to allow work on the laser outside the radiation area.
- Progress with costing. Should have something to circulate on Monday.
- GA to circulate template spreadsheet for costing to WPMs.
- Instrumentation.
- R&D plan
- Meetings with WPMs to update details.
- Should be completed Monday next week.
- Write up
- Review write up in Tuesday meeting next week.
- Laser
Action items
- JPas to send AK beta and alpha as a function of S (calculated by BeamOptics).
- AK to arrange meeting with OE and ZN to discuss R&D plan and write up.
- GA to circulate template spreadsheet for costing to WPMs.
- AK to circulate detailed R&D plan and schedule.
Attachments (1)
-
WS_180220_Stage1Opticsv4.3.pdf
(692.2 KB
) - added by 5 years ago.
New Stage 1 Optics V4.3