wiki:Research/DesignStudy/WPMGroup/Meetings/2022/04-19

LhARA fortnightly Meeting 19th April 2022; 14:00 GMT =

ZOOM: https://imperial-ac-uk.zoom.us/j/95000734107?pwd=eUo1bXpvako5KzhzSlFkTXFKdjFGZz09&from=addon

Meeting ID: 950 0073 4107 Passcode: p+Uu8$

Agenda

  1. Preparation of LhARA proposal

Assume money from UKRI IAC proposal can start 01Oct22; then:

  • Completed text: 08Apr22 - partial success
  • Circulate to collaboration for comment with 1 week deadline; - action completed K. Long Thurs 14th April
  • Finalised document by 22Apr22

This gives 1 week contingency before collaboration meeting

  • Work package reports:
    1. Project Management: J. Parsons, C. Whyte.

Major project deliverables

  • CDR 24
  • TDR1 36
  • TDR2 60
  1. Laser-driven source: E. Boella, N. Dover, R. Gray

Major project deliverables

  • Scapa ion source sim & expt 18
  • Optimisation of proton and Ion source - laser specifiction 30
  • 10Hz operation - advanced targetry 48
  • Stabilised 5Hz at Scapa 59
  1. Ion capture: M. Charlton, W. Bertsche

Major project deliverables

  • Validate plasma Sims 6
  • Larga diameter plasma expt results 18
  • Next generation plasma lens design 23
  • Build progress report 36
  • Ion focussing results 59
  1. Dose-deposition profiling: J. Bamber, E. Harris, J. Mattheson

Major project deliverables

  • Geant 4 Sims 12
  • K-wave simulation and sensor array design 23
  • Iterative reconstruction methods 36
  • Dose mapping - calibration of ion acoustic detection 48
  • Acoustic rig/radiobiology station integration 48
  • 'LhARA' test results 59
  1. Vertical beam line and biological end station development: R. McLauchlan, T. Price

Major project deliverables

  • Report on required new beam monitoring required 23
  • Design report: automated handling facility 23
  • Report: beam monitoring system 59
  • Specification, LhARA beam delivery and monitoring system 59
  1. Accelerator design and integration: N. Bliss, J. Pasternak

Major project deliverables

  • Final review R&D for CDR 18
  • Final review R&D for TDR1 35
  • Final review R&D for TDR2 56
  • Technical review FFA magnet 58
  • Technical review MA cavity 58
  1. DoNM :
    • 19Apr22

  1. AoB

Last modified 2 years ago Last modified on Apr 26, 2022 1:57:15 PM