LhARA fortnightly Meeting 19th April 2022; 14:00 GMT =
ZOOM: https://imperial-ac-uk.zoom.us/j/95000734107?pwd=eUo1bXpvako5KzhzSlFkTXFKdjFGZz09&from=addon
Meeting ID: 950 0073 4107 Passcode: p+Uu8$
Agenda
- Preparation of LhARA proposal
Assume money from UKRI IAC proposal can start 01Oct22; then:
- Completed text: 08Apr22 - partial success
- Circulate to collaboration for comment with 1 week deadline; - action completed K. Long Thurs 14th April
- Finalised document by 22Apr22
This gives 1 week contingency before collaboration meeting
- Work package reports:
- Project Management: J. Parsons, C. Whyte.
- Major project deliverables
- CDR 24
- TDR1 36
- TDR2 60
- Laser-driven source: E. Boella, N. Dover, R. Gray
- Major project deliverables
- Scapa ion source sim & expt 18
- Optimisation of proton and Ion source - laser specifiction 30
- 10Hz operation - advanced targetry 48
- Stabilised 5Hz at Scapa 59
- Ion capture: M. Charlton, W. Bertsche
- Major project deliverables
- Validate plasma Sims 6
- Larga diameter plasma expt results 18
- Next generation plasma lens design 23
- Build progress report 36
- Ion focussing results 59
- Dose-deposition profiling: J. Bamber, E. Harris, J. Mattheson
- Major project deliverables
- Geant 4 Sims 12
- K-wave simulation and sensor array design 23
- Iterative reconstruction methods 36
- Dose mapping - calibration of ion acoustic detection 48
- Acoustic rig/radiobiology station integration 48
- 'LhARA' test results 59
- Vertical beam line and biological end station development: R. McLauchlan, T. Price
- Major project deliverables
- Report on required new beam monitoring required 23
- Design report: automated handling facility 23
- Report: beam monitoring system 59
- Specification, LhARA beam delivery and monitoring system 59
- Accelerator design and integration: N. Bliss, J. Pasternak
- Major project deliverables
- Final review R&D for CDR 18
- Final review R&D for TDR1 35
- Final review R&D for TDR2 56
- Technical review FFA magnet 58
- Technical review MA cavity 58
- DoNM :
- 19Apr22
- AoB