    11= SmartPhantom meeting: Wednesday 21^st^ August 2019, 11:00 BST =
     2
     3== Notes: ==
     4
     5**Present*: KL, HTL
     6
     71. Notes and actions from [wiki:Research/Instrumentation/Meetings/2019/09-13 last meeting]:
     8 * **KL**: Liaise to develop concept for polishing.
     9  * **Ongoing**.
     10 * **KL**: Define light exclusion scheme for 527.
     11  * **Done**.  Progress since last week: occupants of offices beyond the 527 lab informed and on-board with need to exclude short-wavelength light.  OK now to plan to do the "yellow out".  Specification of material sourced by AK passed on to KL.
     12 * **AK**: Prepare paperwork necessary to gain permission to work with source in 527.
     13  * **Ongoing.**
     14 * **AK**: Pass details of second laptop to KL so that delivery can be followed in AK's absense.
     15  * **Superceded**.  Laptop has now arrived.  LabView installed (i.e. Licences are valid).
     16
     172. Baseline schedule and progress against schedule: KL/HTL \\
     18 * [raw-attachment:2019-08-21-SmartPhantom.pdf Progress against baseline schedule].
     19
     203. Mechanical design/manufacture update: JT for LC \\
     21 * Winding jig is complete at RAL and will be shipped to imperial.  Photograph of assembled jig is shown below.
     22
     234. Control system and SciWire readout update: AK \\
     24 * No report this week as AK is on leave.  Item left for future reference.
     25
     265. Simulation/analysis update: HTL \\
     27 * [raw-attachment:meeting.pdf Material/Glue Simulation Update].
     28 * Variation with film material (mylar, kevlar, and kapton) and depth of epoxy studied.  Variation is small.  So we **accept** specification adopted in discussion on 15Aug19: 100 micron mylar sheet and 200 micron depth of epoxy.
     29
     306. Next steps \\
     31 * Move to test winding.
     32
     337. DONM \\
     34 * 28Aug19
     35
     368. AoB \\
     37
     38=== Summary of actions: ===
     39 * **KL**: Liaise to develop concept for polishing.
     40 * **AK**: Prepare paperwork necessary to gain permission to work with source in 527.