SmartPhantom meeting: Wednesday 21st August 2019, 11:00 BST
Notes:
Present*: KL, HTL
- Notes and actions from last meeting:
- KL: Liaise to develop concept for polishing.
- Ongoing.
- KL: Define light exclusion scheme for 527.
- Done. Progress since last week: occupants of offices beyond the 527 lab informed and on-board with need to exclude short-wavelength light. OK now to plan to do the "yellow out". Specification of material sourced by AK passed on to KL.
- AK: Prepare paperwork necessary to gain permission to work with source in 527.
- Ongoing.
- AK: Pass details of second laptop to KL so that delivery can be followed in AK's absense.
- Superceded. Laptop has now arrived. LabView installed (i.e. Licences are valid).
- KL: Liaise to develop concept for polishing.
- Baseline schedule and progress against schedule: KL/HTL
- Mechanical design/manufacture update: JT for LC
- Winding jig is complete at RAL and will be shipped to imperial. Photograph of assembled jig is shown below.
- Control system and SciWire readout update: AK
- No report this week as AK is on leave. Item left for future reference.
- Simulation/analysis update: HTL
- Material/Glue Simulation Update.
- Variation with film material (mylar, kevlar, and kapton) and depth of epoxy studied. Variation is small. So we accept specification adopted in discussion on 15Aug19: 100 micron mylar sheet and 200 micron depth of epoxy.
- Next steps
- Move to test winding.
- DONM
- 28Aug19
- AoB
Summary of actions:
- KL: Liaise to develop concept for polishing.
- AK: Prepare paperwork necessary to gain permission to work with source in 527.
Meeting details
Blackett 521 (The Tutorial Room) and teleconference
Phone details:
UK: 08082 380274 Austria: 0800 006612 PIN: 5904750902
Full list of telephone contacts may be found here.
Agenda:
- Notes and actions from last meeting:
- KL: Liaise to develop concept for polishing.
- Ongoing.
- KL: Define light exclusion scheme for 527.
- Done. Progress since last week: occupants of offices beyond the 527 lab informed and on-board with need to exclude short-wavelength light. OK now to plan to do the "yellow out". Specification of material sourced by AK passed on to KL.
- AK: Prepare paperwork necessary to gain permission to work with source in 527.
- Ongoing.
- AK: Pass details of second laptop to KL so that delivery can be followed in AK's absense.
- Superceded. Laptop has now arrived.
- KL: Liaise to develop concept for polishing.
- Baseline schedule and progress against schedule: KL/HTL
- Mechanical design/manufacture update: JT for LC
- Control system and SciWire readout update: AK
- No report this week as AK is on leave. Item left for future reference.
- Simulation/analysis update: HTL
- Next steps
- DONM
- 28Aug19
- AoB
Last modified
5 years ago
Last modified on Aug 21, 2019, 11:23:01 AM
Attachments (2)
- meeting.pdf (1.3 MB ) - added by 5 years ago.
- 2019-08-21-SmartPhantom.pdf (24.9 KB ) - added by 5 years ago.
Download all attachments as: .zip
Note:
See TracWiki
for help on using the wiki.