SmartPhantom meetings: Wednesday 6th November 2019

Summary of actions:

  • KL: Liaise to develop concept for polishing.
  • LC: Complete detailed design of the boot.
  • HTL will send summary simulations to indicate how close first SciFi layer must be to cell layer.
  • AK: Will send HTL the LabView code.
  • HTL: Request thickness of culture flask window from MP.
  • LC: arrange packing of winding jig and inform HTL who will arrange transport.

Notes:

  1. Notes and actions from last meeting:
    • KL: Liaise to develop concept for polishing.
      • Stands.
    • LC: Complete detailed design of the boot.
      • Stands. Spoke to Cyril; by next week expect i/p.
    • MP: Send autocad drawing of flask holder to LC.
      • Done.
    • LC create drawing of station-holder concept: stations fixed to culture flask and station fixed at entry to water phantom.
      • Done. See slides.
    • MP: Provide trigger-pulse shape.
      • Done. MP provided the following specification:
        • Trigger signal is a TTL (rectangular) standard; duration from 10 ns to 650 us.
    • KL deal with projected overspend on IC IAA account and estimate of resource required from PPD.
      • In progress. Need to discuss projected spend with LC. Money is now tight, but fortunately we've made most of the orders (I hope).
  1. Mechanical design/manufacture update: LC
    Slides.
    • Present solution puts SciFi too far from cell layer. Various ideas to get it closer discussed. LC will look into a design revision.
    • HTL will send summary simulations to indicate how close first SciFi layer must be to cell layer. HTL; assumption was that first plane was 3mm from the cell layer including the thickness of the culture flask.
  1. Single-fibre test setup: HTL
    • Waiting for parts from D.Nardini. Expect to have parts ready by end of the day.
    • HTL requests AK to send LabView code for motor control. AK: Will send HTL the LabView code.
    • HTL/KL begin permissions paperwork for use of radioactive source.
    • Need to find out from MP (HTL) or measure the culture flask so that we know the cell-support layer thickness.
  1. Schedule revision discussion: All
    • No update; still press on to schedule iteration done for Christmas.
  1. Spend: outstanding requirement: All
    • No update.
  1. Next steps: All
    • Arrange transport of winding jig from RAL to IC.
    • LC: arrange packing of winding jig and inform HTL who will arrange transport.
  1. DONM
    • Next Wednesday.

  1. AoB
    • AK: MP and LC now have accounts so that they can access the wiki.

Meeting details

Videoconference using the Vidyo system.

Connection details:

Please join the VIDYO meeting by clicking this link: https://vidyoportal.cern.ch/join/SPJlsfAOEV

If you want to join by phone, please use one of the phone numbers listed in the link below:

http://information-technology.web.cern.ch/services/fe/howto/users-join-vidyo-meeting-phone

The PIN for the phone connection is: 1079548

Agenda:

  1. Notes and actions from last meeting:
    • KL: Liaise to develop concept for polishing.
      • Stands.
    • LC: Complete detailed design of the boot.
    • MP: Send autocad drawing of flask holder to LC.
    • LC create drawing of station-holder concept: stations fixed to culture flask and station fixed at entry to water phantom.
    • MP: Provide trigger-pulse shape.
      • Done. MP provided the following specification:
        • Trigger signal is a TTL (rectangular) standard; duration from 10 ns to 650 us.
    • KL deal with projected overspend on IC IAA account and estimate of resource required from PPD.
      • In progress. Need to discuss projected spend with LC. Money is now tight, but fortunately we've made most of the orders (I hope).
  1. Mechanical design/manufacture update: LC
    Slides.
  1. Single-fibre test setup: HTL
  1. Schedule revision discussion: All
  1. Spend: outstanding requirement: All
  1. Next steps: All
    • Arrange transport of winding jig from RAL to IC.
  1. DONM
    • Next Wednesday.

  1. AoB

Attachments (1)

Download all attachments as: .zip

Note: See TracWiki for help on using the wiki.