| | 11 | |
| | 12 | == Actions == |
| | 13 | |
| | 14 | == Notes == |
| | 15 | Present: Clive Hill, Mark Johnson, Ta-Jen Kuo, Ajit Kurup, Hywel Owen, Matt Pereira, Will Shields, Colin Whyte \\ |
| | 16 | Apologies: Andy Goulden, Ken Long, Jaroslaw Pasternak, Rehanah Razak |
| | 17 | |
| | 18 | * Milestone report |
| | 19 | * Just need to transfer the milestone report to the 18th month. |
| | 20 | * HO: need to add the drawing of the cavity. |
| | 21 | * CH to check the CAD file. |
| | 22 | * Simulation |
| | 23 | * WS: |
| | 24 | * Working on the IPAC paper |
| | 25 | * Looking at beam size in the injection line. |
| | 26 | * Discussion regarding size of the beam, dispersion and beam distribution. |
| | 27 | * TJK: |
| | 28 | * Field clamp design. |
| | 29 | * Looked at attaching the clamp to the yoke. |
| | 30 | * Engineering - CH |
| | 31 | * Showed the cavity CAD models. Ferrite won't fit as it is. MA should |
| | 32 | * Looking at injection line. |
| | 33 | * Need details of the septum. Looked at the EMMA design. |
| | 34 | * Space constraint for the septum and the large injection angle. There is space for a magnet 450mm wide. |
| | 35 | * AOB |