| 10 | |
| 11 | == Actions == |
| 12 | |
| 13 | == Notes == |
| 14 | Present: Clive Hill, Ta-Jen Kuo, Ajit Kurup, Ken Long, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\ |
| 15 | Apologies: Andy Goulden, Mark Johnson, Hywel Owen, Jaroslaw Pasternak |
| 16 | |
| 17 | * Engineering - CH |
| 18 | * Update on the injection line layout. |
| 19 | * Simulations |
| 20 | * TJK: Showed slides on yoke and clamp optimisation discussed at last week's meeting. |
| 21 | * WS: |
| 22 | * In contact with DL re GPT simulation. Should be now fixed. |
| 23 | * Using beam from Ken's code and putting through stage 1. |
| 24 | * Impact of having a permanent magnet quad just after nozzle. |
| 25 | * AOB |
| 26 | * Discussion on what should go in the final report. |
| 27 | * CW: Straw-man outline would be good. |
| 28 | * CH: What about the high-energy transfer line |
| 29 | * Discussion. |
| 30 | * CH: Can WS send details of the locations of the beam line elements. |
| 31 | * Discussion on the RF cavity. |