| 14 | == Notes == |
| 15 | Present: Clive Hill, Ta-Jen Kuo, Ajit Kurup, Ken Long, Jaroslaw Pasternak, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte \\ |
| 16 | Apologies: Andy Goulden, Mark Johnson, Hywel Owen |
| 17 | |
| 18 | * Engineering |
| 19 | * Update from CH |
| 20 | * Schematic has been updated with new yoke design. |
| 21 | * Need to address collisions with the injection region and where the injection line crosses the FFA beam pipe. |
| 22 | * Meeting to discuss FFA issues scheduled for 16th July. |
| 23 | * Discussion on how the yoke geometry can be modified to accommodate the injection septum. |
| 24 | * Preference is to go with the previous version. |
| 25 | * Modelling of the trim coils. |
| 26 | * Detailing of the connections and manifolds. |
| 27 | * JP: Need to update a drift length in the high energy transfer line design before finalising. |
| 28 | * Simulations |
| 29 | * TJK: |
| 30 | * Produced field map for JP to track. |
| 31 | * Update on the power requirement 20kW for 1 half of the magnet. |
| 32 | * WS: |
| 33 | * Looking at using linear optics code beam. |
| 34 | * Comparable to the SCAPA beam. |
| 35 | * Looking the modelling the injection line in GPT. |
| 36 | * KL: how long does generating the beam? |
| 37 | * WS: Of the order of half an hour for 1e6 particles. |
| 38 | * AOB |