Changes between Version 1 and Version 2 of Research/LhARA/ProjectBoard/Meetings/2024/02-20


Ignore:
Timestamp:
Feb 20, 2024, 12:09:51 PM (4 months ago)
Author:
cwhyte1
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Research/LhARA/ProjectBoard/Meetings/2024/02-20

    v1 v2  
    1818Work Package 1. Project management: Deliverables
    1919
    20 • '' D1 Early progress review CDR M6 ''
    21 • '' D2 Interim progress review CDR M12 ''
    22 • '' D3 Pre-CDR Review M18 ''
    23 • '' D4 CDR M24 ''
    24 
    2520• ''' D5 Initial progress review TDR & technical de-risk update M30 '''
    2621• ''' D6 Interim progress review TDR & technical de-risk update M36 '''
     
    2823• ''' D8 Stage 1 TDR & technical de-risk report M48 '''
    2924
    30 
    31 • D9 Pre-TDR2 review M54
    32 • D10 TDR2 M60
    3325Milestones
    3426
     
    4335• ''' M3.3: Progress report on increased voltage penning trap simulations and operation. M36 '''
    4436• ''' M3.4: Final report high voltage penning trap operation. M48 '''
    45 
    46 • M3.6: Ion focussing results M60
    4737
    4838