Design and Integration meeting: 27 February 2024 15:00 GMT

Zoom: https://ukri.zoom.us/j/99571436156

Agenda

  • Simulations.
  • Engineering.
  • AOB

Actions

Notes

Present: Andy Goulden, Clive Hill, Ta-Jen Kuo, Ajit Kurup, Ken Long, Hywel Owen, Matt Pereira, Rehanah Razak, Will Shields, Colin Whyte
Apologies: Jaroslaw Pasternak

  • Simulations
    • Slides from WS
      • Comparison of tracking with different Gabor lens models.
    • Slides from KL
      • Different source models.
      • Comparison of solenoids and Gabor lenses
      • Looked at different beam pipe diameters.
    • First go of the LhARA magnet
      • TJK showed Opera model
  • Engineering
    • CH: working on update of the schematic of the transfer line.
  • Milestone report - CH
    • Text on the controls from Graham Cox.
    • Building concept hasn't changed much so will refer to 12-month report.
    • Update on shielding calculations.
    • Vacuum concept section in progress should be ready soon.
    • Power consumption has not changed so will refer to the 12-month report.
    • RF
      • Not much has changed. Will look to see what was written in the 12 month report and update that.
      • CH has got a CAD model of the RF cavity from Rob Matheson. Can add that to the report.
    • CH can progress the write up and present next week.
  • AOB
    • WS: early bird deadline for IPAC is tomorrow.