Version 1 (modified by 5 years ago) ( diff ) | ,
---|
SmartPhantom meeting: Wednesday 23rd October 2019, 11:00 BST
Notes:
- Notes and actions from last meeting:
- KL: Liaise to develop concept for polishing.
- Stands.
- HTL: Prepare revision to schedule for the next meeting.
- Done. Agenda item.
- HTL: Prepare a revised costing spreadsheet for next meeting.
- Done. Agenda item.
- HTL: Add CCAP note number to the header of the note and post it as a CCAP note.
- Stands.
- AK: Purchase hard-drive to store SmartPhantom data in operation.
- Done. Order placed
- LC: Complete detailed design of the boot.
- Stands. Agenda itme.
- KL: Liaise to develop concept for polishing.
- Mechanical design/manufacture update: LC
- LC reported on the Potting figures.
- LC has discussed his boot concept with Cyril. Concept is to restrain resin with release tape. KL noted that for MICE a 'reservoire' of resin was created by drilling an oversize hole on the 'reverse' side of the boot. LC will also consider this.
- LC has sent a drawing update has been done and sent to D.Nardini. DN is awaiting material (2mm cf sheet).
- JB noted that we would also require a camera enclosure and transport case.
- Single-fibre test setup: HTL
- Preparation for set-up has been completed in 527 Blackett. Some parts manufactured, still awaiting source holder a design for which had been provided to DN by HTL.
- Boot design has been transmitted to DN (has also been manufactured).
- Schedule revision discussion: All
- Revised schedule presented. End-date looks rather too late. Need to press on next prototype.
- Spend: outstanding requirement: All
- Revised spend presented. Close to break even. Can purchase enough fibre for single layer planes.
- Need to make orders asap.
- Visit to MedAustron: All
- KL: Needs to confirm detail with M.Puchalska.
- Next steps: All
- Crack on with programme!
- DONM
- Meet next week 11:00 GMT; 12:00 at MedAustron.
- Meet at MedAustron for an 09:30 start.
- KL: Look into Vidyo, ZOOM, or Skype for this meeting.
- AoB
- None.
Summary of actions:
- KL: Liaise to develop concept for polishing.
- HTL: Add CCAP note number to the header of the note and post it as a CCAP note.
- LC: Complete detailed design of the boot.
- KL: Needs to confirm detail with M.Puchalska.
- KL: Look into Vidyo, ZOOM, or Skype for next week's meeting.
Meeting details
Venue: my office: 1105 Blackett Laboratory. Phone details:
UK: 08082 380274 Austria: 0800 006612 PIN: 5904750902
Full list of telephone contacts may be found here.
Agenda:
- Notes and actions from last meeting:
- Mechanical design/manufacture update: LC
- Single-fibre test setup: HTL
- Schedule revision discussion: All
- Spend: outstanding requirement: All
- Visit to MedAustron: All
- Next steps: All
- DONM
- AoB
Attachments (4)
- smartphantom_221019.png (49.7 KB ) - added by 5 years ago.
- SmartPhantom_Costing.pdf (104.9 KB ) - added by 5 years ago.
- 2019-10-22-LC-report.pdf (112.3 KB ) - added by 5 years ago.
- 2019-10-21-PSG954_PHHE_Kenneth-Long_HTL.pdf (105.6 KB ) - added by 5 years ago.
Download all attachments as: .zip
Note:
See TracWiki
for help on using the wiki.